AUT M1

Projects Highlight in New Zealand

CLIENT: University of Auckland

BUILDER: Fletchers Construction Company

PURPOSE AND SIZE: University Campus with approximate 3505 m²

COMPLETION DATE: December 2016

PROJECT DURATION: 6 Months

ACCESS FLOOR SYSTEM USED: 1)SC Ultra Fix @ 3.0kN 2) SC Ultra Fix @ 4.5kN

PROJECT SCOPE/SPECIFICATION: Raised floor plenum to provide underfloor airflow

PROJECT FEATURES AND HIGHLIGHTS: –

1. Air Highway under the floor for Airflow management in Plenum

2. 850 Seismic Pedestals