CLIENT: SkyCity Casino
BUILDER: Naylor Love Construction Limited
PURPOSE AND SIZE: 540 m²
COMPLETION DATE: March 2020
PROJECT DURATION: 6 Weeks
ACCESS FLOOR SYSTEM USED:
ASP Icon X System @ 9.0kN 150mm FFL – 450 FFL
ASP Urban Interlock System @ 9.0kN 150mm FFL – 450 FFL
PROJECT SCOPE/SPECIFICATION: –
- Supply and installation of 9.0kN Icon X bare paneled access floor to RF01.
- Supply of installation of Braced Pedestals for Seismic compliance to PS1.
- Supply and installation of 9.0kN Urban Interlock access floors to RF02.
PROJECT FEATURES AND HIGHLIGHTS:
- Installation on existing bitumen expoxy for warranty.
- Underfloor fire baffles & fyre boxes.